Requirements Checklist — #2056 mission.py remainder decomposition

Quality gate for the spec. Each item must hold before plan/tasks.

Completeness

  • ✅ Overview states the target (mission.py 4125 LOC / 62 defs / 8 subcommands) and that this mission decomposes the REMAINDER (commit_router pipeline already extracted by 01KVMBD6).
  • ✅ Scope and out-of-scope are explicit (no #2058 tasks.py de-godding, no re-extraction of commit_for_mission, no new functionality).
  • ✅ The 3 mega-functions are named with LOC (finalize_tasks 1227, setup_plan 507, create_mission 281).
  • ✅ The 4 research-resolved seams are named (record-analysis / lifecycle-per-family / parsing-validation / feature-dir-resolution).

Correctness of the critical constraint

  • ✅ Spec states the base is origin/main (c3814ec5a) and does NOT include #2058.
  • ✅ Spec states _planning_commit_worktree / _resolve_planning_placement are LIVE (tasks.py calls them) — verified by grep.
  • ✅ Disposition is RELOCATE into commit_router + repoint tasks.py, never delete (FR-007).
  • ✅ Reconciliation against commit_router's existing _stage_artifacts_in_coord_worktree is called out.

Functional Requirements

  • ✅ FR-001 frozen 8-subcommand CLI surface (byte-for-byte) — Approved.
  • ✅ FR-002 #2056 pointer comment (matches #1623 convention) — Approved.
  • ✅ FR-003 decompose into the 4 seams; D first; one-way imports — Approved.
  • ✅ FR-004 per-seam focused tests ≥90%; direct unit tests for pure parsers/resolvers — Approved.
  • ✅ FR-005 internal decomposition of the 3 mega-functions to ≤15 CC with focused tests — Approved.
  • ✅ FR-006 shim re-exports every ~100 test-patched name — Approved.
  • ✅ FR-007 relocate planning-commit residue + repoint tasks.py (LIVE, do not delete) — Approved.

NFRs / Constraints

  • ✅ NFR maxCC ≤15, ≥90% coverage, ruff + mypy --strict clean, no new suppressions.
  • ✅ C-001 no command/flag changes; C-002 canonical commit_router; C-003 behavior-preserving; C-004 no new suppressions; C-005 golden characterization test FIRST (WP01).

Testability

  • ✅ Each FR maps to a verifiable success criterion (SC-1..SC-8).
  • ✅ Golden CLI characterization test is the named safety net and is sequenced first.
  • ✅ Invariants (INV-1..INV-9 in data-model.md) map to enforcing tests.